Equipment Preparation Prior to Starting Work
7151 Views
Feedback
0 Comments

Favorite
Image for Equipment Preparation Prior to Starting Work

Type:  Lessons Learned

Publisher:  URS CH2M Oak Ridge, Oak Ridge, TN

Published As:  Public

Date: 

Topics:  Operations, Training and Qualification, Waste Management, Radiation Protection

Prejob test and preparation for key equipment in a work activity is necessary to prevent an unanticipated condition. Workers were using a peristaltic pump to transfer liquid into a new drum. After pumping for few minutes, the workers indicated that smoke was being emitted from the vicinity of the pump and drum opening.