Failure to Adhere to a Sound Engineering Design Process Resulted in Rework of Safety Significant Components
7527 Views
Feedback
0 Comments

Favorite
Image for Failure to Adhere to a Sound Engineering Design Process Resulted in Rework of Safety Significant Components

Type:  Lessons Learned

Publisher:  Isotek Systems LLC, Houston, TX

Published As:  Public

Date: 

Topics:  Nuclear/Nuclear Safety, Engineering, Construction/Project Management, Quality Assurance

Contractors operating DOE Hazard Category 2 Nuclear Facilities must use accepted design and procurement methods, including design review by all affected disciplines, and meet all quality assurance constraints when modifying those facilities.